Tuesday, August 19, 2008

Leader of Change 6

I have decided to choose the pavement repair work as my target improvement process. To lead and manage this improvement process, I have collected data for our analysis throughout the North-South Expressway.


Data collected shows that since year 2000, it had been a trend of additional pavement defective locations needed to be repaired throughout North-South Expressway (PLUS) via work order.


From the record in year 2006, originally 81 locations were planned (identified) to be repaired but an additional of 25 defective locations were repaired amounting to RM11.9 million and as for year 2007, 23 additional locations amounting to RM8.5 million of works have been issued.


Due to these additional locations, our approved budget could not accomodate to amount of the additional required works. To overcome this problem, we had identified one process where the budget otimisation could be practised.


As part of the exercise, we had analyse the process flow of the works awarding process. From the dsign face, we observed that the design quantity could be optimise. During the analysis stage of the process and data gathered from site, we found that the quantity estimated during the design was provided with extra percentage of quantity and when site implementation at site, the actual works is much less quantity compared to the original design quantity.



Currently, we are in the contol stage of the sute implementation. From the monitoring results, the optimisation process is showing some good results though. The change (improvement) in the process is slowly penetrating the heart of the designer and also the site personal. This can be observed from their design quantity as compared to the actual final quantity at site.