I have decided to choose the pavement repair work as my target improvement process. To lead and manage this improvement process, I have collected data for our analysis throughout the North-South Expressway.
Data collected shows that since year 2000, it had been a trend of additional pavement defective locations needed to be repaired throughout North-South Expressway (PLUS) via work order.
From the record in year 2006, originally 81 locations were planned (identified) to be repaired but an additional of 25 defective locations were repaired amounting to RM11.9 million and as for year 2007, 23 additional locations amounting to RM8.5 million of works have been issued.
Due to these additional locations, our approved budget could not accomodate to amount of the additional required works. To overcome this problem, we had identified one process where the budget otimisation could be practised.
As part of the exercise, we had analyse the process flow of the works awarding process. From the dsign face, we observed that the design quantity could be optimise. During the analysis stage of the process and data gathered from site, we found that the quantity estimated during the design was provided with extra percentage of quantity and when site implementation at site, the actual works is much less quantity compared to the original design quantity.
Currently, we are in the contol stage of the sute implementation. From the monitoring results, the optimisation process is showing some good results though. The change (improvement) in the process is slowly penetrating the heart of the designer and also the site personal. This can be observed from their design quantity as compared to the actual final quantity at site.
Tuesday, August 19, 2008
Sunday, August 10, 2008
Leader of Change 5
It looks like the controlling period of the proposed change is actually the uphill task of all the change implemenation process. Relatively, monitoring of the control progress seems tough due to the incoming data in parts from the various site of the operation.
Some of the results shows that the change was implemented and shows positve impact but at the other hand there are few locations still under familiarisation mood of the change due to the fear of under estimate of the works quantity. This makes the proposed repair works designer have the mind set of so sceptical of the volume or size of defect measured during the site assessment carried out before the design. Thus, turn the designer to provide extra provisional size of defects to avoid uncovered defects during the site assessment.
Some of the results shows that the change was implemented and shows positve impact but at the other hand there are few locations still under familiarisation mood of the change due to the fear of under estimate of the works quantity. This makes the proposed repair works designer have the mind set of so sceptical of the volume or size of defect measured during the site assessment carried out before the design. Thus, turn the designer to provide extra provisional size of defects to avoid uncovered defects during the site assessment.
Thursday, August 7, 2008
Leader of Change 4
This week (fourth week) after attending the programme of LOC, I am more focus and could storm my brain better on waht to be done for change. I have noticed that there is force inside our staff involved in the change process. They are more aware of change motive and target with the positive note of intention of the company future as well as individual. Base the outcome of the monitoring of the process, there are substancial improvement in the process implementation.
As for me, I am quite aware that these Leader of Organisational Change do improve the works process in a company with the change in mentality of attending individual. Going back to basic of management where a leader shoud always try to look for improvement in the organisation. Thus, a leader who had attended the Leading Orgaisational Change will definitely gain the knowledge of change methods that can be applied along with their daily activities at office and also anywhere they go.
For our staff who are involved in the process change, they feels that the idea should be learn and given to the rest of the organiation. May be not limited to the managers only but also to the management executive who involve in the organisation business flow.
Looks like everyone in the company needs to obtain these knowledge from other perpective or angle that are relevant to their works finction and life expectation. I my self hope that all staff aware the change and provide the full support to the company viin and mission.
As for me, I am quite aware that these Leader of Organisational Change do improve the works process in a company with the change in mentality of attending individual. Going back to basic of management where a leader shoud always try to look for improvement in the organisation. Thus, a leader who had attended the Leading Orgaisational Change will definitely gain the knowledge of change methods that can be applied along with their daily activities at office and also anywhere they go.
For our staff who are involved in the process change, they feels that the idea should be learn and given to the rest of the organiation. May be not limited to the managers only but also to the management executive who involve in the organisation business flow.
Looks like everyone in the company needs to obtain these knowledge from other perpective or angle that are relevant to their works finction and life expectation. I my self hope that all staff aware the change and provide the full support to the company viin and mission.
Sunday, August 3, 2008
Leader of Change 3
I am writing what is my observation for the third week in my office after attending the Leading Organisation Change. It looks like our staff doing the controlling the proposed change was still in the mood of monitoring the progress of the change and it seems that the input is coming part by part from the various site of the operation. Some of the results could be seen that the change was implemented at a moderate intensity due to site and operation staffs are still under familiarisation mood and coping the culture of the change in the process. It make the site people feel they are being monitored thus make the execution of works being carried out with more careful and more optimum product or result. I will be keeping both my eyes on these for the next few weeks hoping that it will progress according to plan. Work for the best and hope the better turn right.
Sunday, July 20, 2008
Leader of Change 2
This week (second week) upon attending the programme of LOC, I more fresh and ready to think of what to be done. I have foresee a chance of enhancement on what we are doing for betterment.
Firstly, I would need to brief and discuss with staff related to the work and process intended to be change. Then, I would brainstorm with the team of what to done in order to make any change on the current process. I will make sure that a clear vision of the change will be communicated through the team. I had reviewed the current process which had been the target for change enhancement. From the desk, it is progressing but somehow require tighter monitoring to control the achievement.
Firstly, I would need to brief and discuss with staff related to the work and process intended to be change. Then, I would brainstorm with the team of what to done in order to make any change on the current process. I will make sure that a clear vision of the change will be communicated through the team. I had reviewed the current process which had been the target for change enhancement. From the desk, it is progressing but somehow require tighter monitoring to control the achievement.
Wednesday, July 16, 2008
Leader of Change
I just came back to office this morning around 7.40a.m. Reaching my desk which I left for three days to attend the Leading Organisational Change at our very own UEM Leadership Centre from 14 to 16 July 2008, I feel something different somewhere but could not figure it out.
Entering the training room was something different from any other training or seminal that I have attended previously. Frankly speaking, during the first day of the programme, I have the feeling like attending my first class in a university lecture that will face a very determine lecturer with a few friends paying total attention on the topic and not forgetting those with blank faces too. Mix feeling on the upcomimg lecture I could say but with the very detetermine speaker who was the facilitator (Cliff), inside my heart came a motivated word to try to pick what ever will be presented during the lecture period.
Now that I am back in office, with the new knowledge in me, I feel like some thing could be change to enhance any of the current process or activity. However, I am yet to figure out what change I could propose.
To be continues.
Johari
PLUS Expressways Bhd
Entering the training room was something different from any other training or seminal that I have attended previously. Frankly speaking, during the first day of the programme, I have the feeling like attending my first class in a university lecture that will face a very determine lecturer with a few friends paying total attention on the topic and not forgetting those with blank faces too. Mix feeling on the upcomimg lecture I could say but with the very detetermine speaker who was the facilitator (Cliff), inside my heart came a motivated word to try to pick what ever will be presented during the lecture period.
Now that I am back in office, with the new knowledge in me, I feel like some thing could be change to enhance any of the current process or activity. However, I am yet to figure out what change I could propose.
To be continues.